CONSTRUCTION PROGRESS! |
|
Breaking Ground, March 30, 2009 |
![]() Bringing in more dirt from Shadle, April 1 |
|
![]() April 10 |
![]() Preparing for concrete, April 15 |
|
![]() Pouring the concrete footings, April 16 |
![]() April 28, 2009 |
|
![]() The steel frame is going up, May 12 |
The steel beams are being set on top, May 14 |
|
![]() Preparing for more concrete, May 19 |
![]() May 21 |
|
![]() Concrete is poured, May 21 |
![]() More framing, May 27 |
|
![]() Walls going up, May 28 |
![]() June 3 |
|
![]() Framing the entrance, June 4 |
![]() A view from the inside looking out glass doors, June 4 |
|
![]() Perspective from a little ways off, June 16 |
![]() Another view of the inside, June 16 |
|
![]() Almost ready for the roofers, June 18 |
![]() View from Providence south side, June 18 |
|
![]() Working on the roof, June 23 |
![]() Inside of Worship Center is coming along, June 30 |
|
![]() Working on the roof and brick, July 28 |
![]() View from south side; brick going up, July 30 |
|
![]() Roofing complete; siding going up, August 8 |
![]() Siding going up on south side, August 8 |
|
![]() Inside drywall, August 8 |
![]() Inside drywall just about done, August 11 |
|
![]() View of the new trees, August 11 |
![]() Almost ready for paint, August 27 |
|
![]() Preparing for asphalt, August 27 |
![]() Siding & trim done, August 27 |
|
![]() North, September 1 |
![]() South, September 1 |
|
![]() Parking lot lines are painted, September 16 |
![]() South, September 16 |
|
![]() Trusses and lights! September 16 |
![]() Laying the Carpet, October 6 |
|
![]() Carpet finished, October 26 |
![]() Front Entrance, October 26 |
|
![]() Lobby with new Info Center, October 26 |
![]() Walkway from Worship Center to Fellowship Hall |
|
|
COMPLETED WORSHIP CENTER NOVEMBER 22, 2009 |
||
![]() |
![]() |
|
![]() |
![]() |
|
|
Connecting the Pieces, Building the Future Pledges and donations to date: $327,595 Praise the Lord! God is faithful! Thanks and praise go to Him for all He is doing in our church. The story He has written and continues to write here at Garland is an amazing one filled with hope and life! Remember, we are the church and not a building! Keep watching this page for updates... |
||
|
Click here to listen to the message from February 3, 2008 by Pastor Rod Cosgrove "Connecting the Pieces, Building the Future" |
Click here to listen to the message from March 9, 2008 by Pastor Rod Cosgrove "On Temples, Tools & Utensils" 2 Chron. 29 |
|